Gateway Tunnel Work Will Pause if Fed Funding is Not Restored

Four major procurements that comprise the remaining construction packages for the new tunnel are also impacted by the federal funding pause.

Gateway Tunnel Work Will Pause if Fed Funding is Not Restored
Manufacturing of the two tunnel boring machines that will be used for the Palisades Tunnel Project was completed last month.

NEW YORK—One of the largest ongoing public works construction projects in the New York City metro region may be forced to halt construction due to funding issues with the Trump administration.

The Gateway Development Commission announced on Jan. 27 that construction of the Hudson Tunnel Project will pause in early February if disbursements of federal funds do not resume in the coming days.

GDC notified the contractors working on the Hudson Tunnel Project on Jan. 27 that funding for construction will run out on Feb. 6. GDC’s contractors will spend the next two weeks winding down work at the active construction sites in New York, New Jersey, and the Hudson River. At that time, construction will stop until additional funding becomes available.

Four major procurements that comprise the remaining construction packages for the new tunnel are also impacted by the federal funding pause. Two construction packages—the Hudson River Tunnel Project and the NJ Surface Alignment Project—are planned to start in 2026, but contracts cannot be awarded until funding resumes.

GDC CEO Thomas Prendergast said, “Over the past two years, GDC, together with our federal and state partners, have made significant progress building the most urgent passenger rail infrastructure project in the country. The progress we have made since the project started construction would not have been possible without the support of the federal Administration. Since federal funding was paused in October, we have done everything in our power to keep construction moving forward as planned, but we cannot fund this work on credit indefinitely. Pausing construction is the absolute last resort, and we will continue working around the clock to secure funding so that the workers who are counting on this project to pay their bills can stay on the job and we can continue delivering the reliable, 21st century infrastructure America needs.”

A total of 70% of the Hudson Tunnel Project’s $16-billion budget – roughly $12 billion—is funded by federal grants. The other $4 billion is funded through USDOT Build America Bureau loans to be repaid by the States of New York and New Jersey and by the Port Authority of New York and New Jersey. Funding disbursements from all of these sources have been discontinued since October 1 of last year.

GDC has signed and executed funding agreements with all Hudson Tunnel Project funders, including the US Department of Transportation (USDOT), the Federal Transit Administration (FTA), and the Federal Railroad Administration (FRA). $4.38 billion in federal funding is currently obligated to the project.

On Sept. 30, 2025, GDC received a notice from the FTA that federal disbursements under the Capital Investment Grants (CIG) Program would be paused pending a review of the commission’s federally mandated Disadvantaged Business Enterprise (DBE) program. The following day, all federal funding for the Hudson Tunnel Project—not just CIG funds—was paused.

Construction has continued while federal funding disbursements have been paused. Since Oct. 1, GDC has:

  • Procured two tunnel boring machines. The first is on site in New Jersey, ready for assembly, and the second is scheduled to be shipped in February.
  • Finished the Tonnelle Avenue bridge and made significant progress on the portal launch box, setting the stage for tunnel boring to begin in New Jersey.
  • Completed two major concrete pours for HYCC-3, totaling more than 7,200 cubic yards, and broke through the bulkhead, connecting to the completed sections of the concrete casing.
  • Mixed 84 primary columns and 112 secondary columns of reinforced earth in the Hudson riverbed, bringing the total number of finished columns to 838.
  • Installed 29 slurry wall panels for the Hudson County Access Shaft and 15 panels for the 12th Avenue Access Shaft. The Hudson County Shaft slurry wall is now more than 75% finished.

Pausing construction will result in the immediate loss of nearly 1,000 jobs. An extended pause would put at risk approximately 11,000 construction jobs on the current projects, as well as the 95,000 jobs and $19.6 billion in economic activity that construction of the Hudson Tunnel Project is anticipated to generate overall.

Author
Real Estate In-Depth

Real Estate In-Depth is the official publication of the Hudson Gateway Association of Realtors.

View articles

Great! You’ve successfully signed up.

Welcome back! You've successfully signed in.

You've successfully subscribed to Real Estate In-Depth.

Success! Check your email for magic link to sign-in.

Success! Your billing info has been updated.

Your billing was not updated.